Dear Members,
The 5th hearings was held on 7th May 2016
before the Hon’ble Arbitrator and in terms to last hearing the case proceed as
under:
1.
A detailed joint inspection/survey on mutually
agreed date be undertaken by the officers of Haryana Govt. and the Durga
Builders Pvt. Ltd. to determine the extent of encroachment over the licensed
land in Phase-I & II before the next date of hearing.
2.
Land verification of the entitlement in hand of
the occupier be ascertained.
3.
Cut-off date be fixed to determine the entitlement of the genuine/bonafide plot holders as below:
-Booking of plot before 07-4-1997 & its complete
payment regularly.
-Payment of entire development Charges up to
31-12-1999 as already decided by Hon’ble Supreme Court of India.
4. The payment
of cost of land after 07-04-97 and dev. Charges after 31-12-1999 can also
be considered if they will ready to pay the actual cost of present estimate.
We have already filed a fresh list of our
members who are in touch of Association and paying their contribution.
. The next hearing is on 3rd June 2016.
The final order is still awaited.
PLEASE LOG-ON THIS BLOGGER FOR FACTUAL INFORMATION.